Pilz PSENvip RL D P Instrukcja Użytkownika Strona 106

  • Pobierz
  • Dodaj do moich podręczników
  • Drukuj
  • Strona
    / 139
  • Spis treści
  • BOOKMARKI
  • Oceniono. / 5. Na podstawie oceny klientów
Przeglądanie stron 105
7.5 Check protective equipment
7 Commissioning
Pilz GmbH & Co. KG, Felix-Wankel-Straße 2, 73760 Ostfildern, Germany
Telephone: +49 711 3409-0, Telefax: +49 711 3409-133, E-Mail: [email protected]
7-24
Fig. 7-21: Function test using test rod
The test rod must be detected along the whole length of the detection
zone.
The OSSDs switch to the OFF state. The LED on the receiver lights up
red.
Function test with 10 mm and 15 mm test piece
Position the 10 mm high section of the test piece on top of the lower
tool.
Initiate a press stroke.
Fig. 7-22: Function test using test piece
INFORMATION
The following tests must be run on the left- and right-hand end
as well as in the centre of the press brake:
- During initial commissioning: 10 times
- During the daily check and during a tool change: 3 times
Przeglądanie stron 105
1 2 ... 101 102 103 104 105 106 107 108 109 110 111 ... 138 139

Komentarze do niniejszej Instrukcji

Brak uwag